01Understand the mechanismInspect the relevant process stages.
02Review the operating dutyKeep assumptions and measured values visible.
03Prepare the next decisionUse the guide, tools and project checks.
INTERACTIVE PROCESS ATLAS

See the mechanism.
Understand the duty.

Select a route or a stage to inspect the process. The cutaway explains the equipment and water environment; it is a teaching illustration, not a project drawing.

Swipe horizontally to inspect the equipment. Stage buttons below also centre the selected component.
Inside a recirculating aquaculture treatment systemA cutaway culture tank connects to a rotary drum screen, moving bed biofilter, degassing tower, sump and pump, oxygen cone and enclosed UV reactor. Blue arrows follow recirculating water. An amber line takes drum-filter waste out of the loop. Equipment shapes and motion explain the process; dimensions and timing are illustrative.SEPARATE WASTE ROUTE VENTILATED OFF-GASCONTROLLED O₂ SUPPLY01 CULTURE TANK02 DRUM SCREEN03 MOVING BED04 DEGASSING05 SUMP + PUMP06 OXYGENATION07 UV TREATMENTTAN-NNH₄⁺ → NO₂⁻ → NO₃⁻PUREFLOW / INTERACTIVE PROCESS ATLASCONCEPT LAYOUT · NOT TO SCALE
Follow culture water through the coordinated treatment train and back to the stock.
Selected process stage

Culture tanks

Collect waste before it settles.

How it works

The culture tank is both an animal environment and a hydraulic vessel. The return flow should distribute oxygenated water and move settleable waste toward the intended outlet. Tank shape, drain arrangement and the behaviour of the stock determine how well this happens.

What to establish
  • Confirm the operating water volume and peak feed.
  • Check circulation, drain capture and access for inspection.
  • Record oxygen at the animal zone, not only in the return pipe.

Read about biomass and loading ↗

Filtration mode. Wash sequence and timing are illustrative. Geometry, stage order, pipe routes and equipment configuration are conceptual. Use the approved project design, operating instructions and verified model data.

Key takeaways

  • What fails first: Aeration and circulation.
  • Backup power: A generator sized for the critical loads: aeration, main circulation and controls.
  • Oxygen backup: A stored oxygen supply with a simple, power-free delivery path gives you extra time.
  • Alarms: Alarm on power loss, low flow, low oxygen, high water level and high temperature.
Reference illustration for RAS Power Backup and Alarms: Planning for the Day Everything Stops
Equipment reference visual; not evidence of a completed installation.
THE SHORT ANSWER

What fails first

Aeration and circulation. Dense stocking can exhaust oxygen quickly once pumps stop, so the first priority is keeping air or oxygen going.

RAS Power Backup and Alarms - Pureflow Bio
Reference visual. Equipment configuration and project details must be confirmed separately.
AQUACULTURE & RAS

Backup power

A generator sized for the critical loads: aeration, main circulation and controls. Add an automatic changeover so it starts without someone being there. Test it under load, regularly.

PLANNING WORKBENCH

Work with your own numbers.

Use the tools below to explore the relevant arithmetic. Enter measured values or declared assumptions. An estimate does not establish equipment capacity, biological performance or a safe operating limit.

Feed & loading scenario

Translate a selected feeding rate and assumed waste yield into a planning load.

Assumptions and limits

The feeding rate and TAN yield are supplied assumptions. Use the species, feed, growth stage and verified process design; the estimate is not a Pureflow capacity rating.

—Daily feed · kg/day
—Estimated TAN-N · kg/day
Enter your values, or load the labelled arithmetic example. No design values are pre-filled.
FormulaFeed = biomass × feeding rate ÷ 100. TAN-N = feed × assumed yield ÷ 1,000.
Convert units before you calculate
Choose units and enter a value.

Planning arithmetic · inputs remain visible for review · example values are not operating recommendations

AQUACULTURE & RAS

Oxygen backup

A stored oxygen supply with a simple, power-free delivery path gives you extra time. See dissolved oxygen and our oxygen cones.

AQUACULTURE & RAS

Alarms

Alarm on power loss, low flow, low oxygen, high water level and high temperature. Alarms are only useful if they reach someone, so send them to phones, not just a siren.

AQUACULTURE & RAS

Practise

Run a drill. Switch off the main supply and see how long the system holds, who responds and what breaks. Fix the gaps you find.

PROJECT REVIEW

Review the design at peak load

Use these questions to prepare a project brief or an operating review. Check an item only when the information has been recorded for your installation.

0 of 3 checked

This checklist is a working aid in the current page session, not a saved maintenance record.

QUESTIONS

RAS Power Backup and Alarms FAQ

How long do I have in a power cut?

It depends on stocking and temperature. Dense systems can run short in minutes, so do not guess.

Is one generator enough?

For critical systems, many farms also keep a spare.